CLOMR vs LOMR: What Each FEMA Letter Does and When You Need It

A CLOMR is FEMA's comment on a project that has not been built yet. A LOMR changes the effective flood map after it has. Here is how to tell which one a project needs, and how the two fit together.

By Floodway Field GuideUpdated Floodplain Studies

At a glance

CLOMR and LOMR at a glance
QuestionCLOMRLOMR
Full nameConditional Letter of Map RevisionLetter of Map Revision
What it isFEMA's comment on whether a proposed project, if built as proposed, would meet minimum NFIP standards and how it would change the flood hazard information.FEMA's letter officially revising the effective map (FIRM, and the Flood Insurance Study report where needed) to show changed floodplains, floodways or flood elevations.
Changes the effective map?No. The effective FIRM still governs permitting and flood insurance.Yes, from the effective date stated in the letter.
Conditions it reflectsProposed: design plans and a post-project hydraulic model.Existing: as-built survey and plans for a completed project, or new and better data for an unchanged stream.
TimingBefore construction starts.After construction, or whenever better data shows the effective map is wrong.
Required by NFIP rules whenA floodway encroachment would raise the base flood elevation at all, or, where no floodway is designated, development would raise it more than 1.0 foot (44 CFR 60.3(c)(13) and (d)(4)).A project or other physical change alters the flood hazard information. The community must submit the data within six months of it becoming available (44 CFR 65.3).
ApplicationMT-2 forms, online or by mail.MT-2 forms, online or by mail.
Endangered Species ActFEMA requires documentation of ESA compliance before it will process the request.Not part of FEMA's review. The project still has to comply with the ESA on its own.
Review feeYes, with exemptions. See FEMA's Flood Map-Related Fees page.Yes, with exemptions. See FEMA's Flood Map-Related Fees page.

The short answer

A CLOMR comes before construction and a LOMR comes after it. The CLOMR is FEMA's review of a design: it says whether the project, built as proposed, would meet National Flood Insurance Program (NFIP) minimum standards, and what the revised flood hazard information would be. It does not change the map, it is not a permit, and it does not change anyone's flood insurance requirement.

The LOMR is the revision itself. Once it takes effect, the effective Flood Insurance Rate Map (FIRM) shows the new floodplain boundary, floodway or base flood elevations (BFEs), and permitting and insurance follow it. A LOMR can follow a CLOMR, follow a project that never needed one, or correct a map with better data where nothing was built at all.

Both are requested on FEMA's MT-2 forms and reviewed against the same regulations (44 CFR Parts 60, 65 and 72). The difference is what they rest on: a CLOMR rests on what you intend to build, a LOMR on what is on the ground.

When a CLOMR is required

Under NFIP minimum standards a community may not permit development that raises the base flood elevation beyond set limits unless it first gets FEMA's conditional approval. Two triggers cover most projects:

  • Encroachment in a regulatory floodway that would cause any increase in the base flood elevation (44 CFR 60.3(d)(3) and (d)(4)). Floodway projects are normally held to zero rise, shown with a no-rise certification; a project that cannot show zero rise needs a CLOMR before the community can permit it. To check whether a site is in the floodway or only the floodplain, see floodway vs floodplain.
  • Development in Zone AE or A1–30 where no floodway is designated that, together with all other existing and anticipated development, would raise the base flood elevation by more than 1.0 foot at any point (44 CFR 60.3(c)(10) and (c)(13)).

When a CLOMR is needed because a project raises the BFE, 44 CFR 65.12 adds conditions of its own: an evaluation of alternatives that would not raise the BFE and why they are not feasible, individual legal notice to every affected property owner, concurrence from the chief executive officer of any other community affected, certification that no structures sit in the area the higher BFE would reach, and requests to revise the BFEs (65.6) and the floodway (65.7).

Many states and communities set stricter standards than these minimums, such as a smaller allowable rise or a CLOMR for every project that changes the floodway. Check the local floodplain ordinance and ask the community floodplain administrator or state NFIP coordinator before design is fixed. Outside these triggers, a CLOMR is optional, but owners and developers often request one anyway to confirm a design will lead to the map change they are counting on.

The bridge and culvert crossings this site covers are the common case: see HEC-RAS bridge modeling for no-rise certification for showing zero rise, and the culvert replacement LOMR case study for what happens when a project skips the CLOMR it needed.

When a LOMR is required

A community has to keep its flood maps current. Under 44 CFR 65.3, as soon as practicable and no later than six months after the information becomes available, it must submit technical or scientific data showing physical changes that affect flood hazard information. In practice that means a LOMR:

  • after any project built under a CLOMR, using as-built data;
  • after a project that did not need a CLOMR but still changed the BFEs, the floodway or the floodplain boundary, such as a culvert or channel improvement that lowers flood elevations;
  • when better hydrology, survey or terrain shows that the effective map is wrong, with no project involved.

A zero-rise floodway project usually needs no CLOMR, but it can still need a LOMR afterwards if it changes what the map shows. Settle that question when the project is scoped, not when it is finished.

How a project moves from CLOMR to LOMR

  1. Scope with the community. Confirm with the floodplain administrator (and the state NFIP coordinator) which letters the project needs and which local standards apply.
  2. Build the model chain. Obtain the effective model and reproduce it (the duplicate effective model), correct it if it has errors (corrected effective), add existing site conditions (existing or pre-project) and then the design (proposed or post-project).
  3. Submit the CLOMR. Complete the MT-2 forms, with the community's signature on Form 1, the ESA documentation, the 65.12 items where the BFE rises, the models and work maps, and the fee. Submit through FEMA's Online LOMC tool or by mail; in some states a Cooperating Technical Partner processes MT-2 requests instead.
  4. Answer FEMA's data requests. The reviewer may ask for more data or corrections before issuing the conditional letter. The letter sets out what the LOMR will need.
  5. Build the project after the community issues its floodplain development permit. The CLOMR is not a permit.
  6. Survey the as-built condition and update the post-project model to match it. Where construction departed from the CLOMR design, show the effect of each change.
  7. Submit the LOMR on the MT-2 forms with certified as-built data, the revised models and work map, and the CLOMR case number.
  8. Wait for the effective date. When a LOMR changes BFEs, FEMA publishes notice of the proposed change and allows a statutory 90-day appeal period. The letter states the date the revision takes effect.

The models are where most delays start. The HEC-RAS output documentation guide covers how to keep each model condition distinguishable in the package, and HEC-RAS 2D vs 1D model selection for FEMA submittals covers choosing the approach the reviewer will accept.

What goes in the MT-2 package

CLOMR and LOMR requests use the same MT-2 form set. A riverine request typically includes:

  • Form 1, Overview and Concurrence, signed by the requester, the certifying engineer and the community official;
  • Form 2, Riverine Hydrology and Hydraulics, describing the hydrology and the hydraulic models used for each condition;
  • Form 3, Riverine Structures, where the project includes a bridge, culvert, channelization, levee or dam;
  • the digital model files for every condition, with the plan names that support each comparison;
  • a certified topographic work map showing the effective and revised floodplain and floodway, and an annotated FIRM;
  • for a CLOMR: the proposed plans, the ESA compliance documentation and, where the BFE rises, the 44 CFR 65.12 items;
  • for a LOMR: certified as-built plans and survey, and a reference to any CLOMR issued for the project;
  • the review fee, unless the request qualifies for an exemption.

FEMA's MT-2 instructions and its MT-2 guidance document are the authority on what a given request needs. Check the current versions before assembling a package, since FEMA revises both.

Mistakes that cost time

  • Treating the LOMR as the only milestone on a floodway project that raises the BFE. Without a CLOMR, the community could not lawfully permit the work, and the fix is far harder after construction.
  • Reading a CLOMR as approval to build. The local permit is still required, and the effective map still governs until the LOMR takes effect.
  • Letting the as-built drift from the CLOMR design without re-running the model. Changed openings, grades or fill limits all have to be accounted for in the LOMR.
  • Missing the six-month window under 44 CFR 65.3 once as-built data exists.
  • Skipping the duplicate effective model. If the effective model cannot be reproduced, every comparison built on it is open to question.
  • Forgetting the people affected. Where a CLOMR raises the BFE, notice to each affected owner is a requirement, not a courtesy.

For how firms price the work across both phases, see how small engineering firms price and scope LOMR projects.

Where to check fees, forms and timelines

Fees, forms and processing practice change, so check them at the source rather than relying on a figure from an old project:

  • review fees and exemptions: FEMA's Flood Map-Related Fees page (online submittals carry a lower fee than paper);
  • forms, instructions and mailing addresses, including the states where a Cooperating Technical Partner reviews MT-2 requests: FEMA's LOMR and CLOMR page;
  • local standards and whether a project needs a CLOMR: the community floodplain administrator and the state NFIP coordinator;
  • how long a review will take: the FEMA reviewer or Cooperating Technical Partner assigned to the case, since the clock depends on when the submittal is complete.

Questions

Does a CLOMR change flood insurance requirements?

No. A CLOMR does not revise the map, so lenders, insurers and the community keep using the effective FIRM. Only a LOMR, once effective, changes what the map shows.

Can construction start once the CLOMR is issued?

Only once the community issues its floodplain development permit and any other permits the project needs. FEMA's comments on a proposed project are not a permit or an approval of the development.

Does a no-rise project need a CLOMR?

Not under NFIP minimum standards, if the no-rise certification shows zero increase in the floodway. The community may still require one, and the project may still need a LOMR afterwards if it changes the flood hazard information.

How is a LOMR different from a LOMA or LOMR-F?

A LOMA (amendment) removes a property or structure on naturally high ground from the Special Flood Hazard Area, and a LOMR-F does the same for one raised by fill. Both are requested on MT-1 forms and leave the flood elevations alone. A LOMR, on MT-2 forms, revises the flood hazard information itself: the BFEs, the floodway or the floodplain boundary along a reach. See LOMA vs LOMR for all three side by side.

How long does each take?

It depends on how complete the submittal is and how many data requests follow. FEMA's review runs from when it has everything it needs, and a LOMR that changes BFEs also waits out the 90-day appeal period before taking effect. Ask the assigned reviewer for the current timeline.

Sources

Regulations and FEMA guidance change. Confirm requirements against the current versions of these sources before relying on them for a submittal.